I noticed other reports such as JXLS have the option to 'schedule' whereas Groovy scripts do not seem to have such an option. Is it possible to schedule Groovy scripts, and if so how should I go about doing it?
When I try selecting a groovy report when creating a new scheduler job under the Scheduler tab, I get the following error message, which I am not sure how to resolve: "The chosen configuration is invalid."
Thank you in advance!
Offline
Hi Johann,
you can schedule script reports analogously as any other report type, so this should not be an issue. You have to first make sure the script report works. Infos on script reports: https://reportserver.net/en/guides/scri … Reporting/
If you want to directly schedule a script, not a report, you can as explained here: https://reportserver.net/en/guides/scri … g-Scripts/
Regards,
Eduardo
Offline
To clarify, I am trying to schedule a report.
The reports I have are working alright, I can set parameters and preview the report. However, it’s just that after selecting the report in the Scheduler, I am unable to click on “Submit”, and if I try to click on “Next” I get the above error message.
Offline
Hi Johann,
could you pls post some screenshots where exactly do you click for scheduling, how is the report configuration, etc? You can use http://imgbb.com for this. Also pls post the exact reportserver version (administration -> system console)
Are you trying to schedule a base report or a variant ?
Regards,
Eduardo
Offline
could you pls post some screenshots where exactly do you click for scheduling, how is the report configuration, etc?
I select the report after clicking on "New Scheduler Job": https://ibb.co/gt0Zrvm
I get the following error: https://ibb.co/B68vcZW
Also pls post the exact reportserver version (administration -> system console)
I am using version 3.71: https://ibb.co/BgxGC5B
Are you trying to schedule a base report or a variant ?
I believe it is a variant.
Last edited by Johann (2022-06-01 02:22:32)
Offline
I have been trying again but am still unable to select Groovy Reports for scheduling. Is there anything else I can try to troubleshoot?
Any help or advice would be greatly appreciated. Thank you!
Edit: Issue was that the export format was not set. Once the export format was set, the configuration was accepted and the scheduling worked.
Last edited by Johann (2022-06-01 06:56:32)